San Francisco-Oakland Bay Bridge Seismic Retrofit Project
Client:
City of Oakland, California
The
Bay Bridge project consisted of retrofitting 16 spans along the east
approach. The spans had the following composition: 6 spans of steel
girder upper deck structure and reinforced concrete T-beam lower deck,
4 spans of steel girder single deck structure, and 6 spans of reinforced
concrete T-beam single deck structure. The retrofit work consisted of:
driving and drilling additional piling to enlarge and reinforce existing
foundations; removing and replacing several existing columns; reinforcing
existing structural steel members and installing restraining systems
throughout the structure. The removal of existing columns and reinforcement
of structural steel members involved the installation of major structural
steel temporary supports. This minimized the inconvenience to the public
by maintaining traffic on both levels of the Bay Bridge.
TRS provided construction field/office engineering and inspection services
for this project. TRS staffed the construction management team with
a Structure Representative, an Assistant Structure Representative and
an Office Engineer. A considerable amount of time was spent reviewing
contract documents, in order to establish the validity of potential
claims for additional compensation or time extensions. Substantial claims
were filed by the contractor for changes and delays caused by conflicts
in the specifications and plans. TRS assisted in resolving the problems
encountered, and as a result the project moved forward quickly and efficiently.
In addition, TRS’ Structure Representative supervised a multitude
of field and office staff to administer the contract.

|